What would the order of subcontractors be to finish a basement?
HVAC
Framing
Electrical
Are those the first three?
Start a related thread
Start a related poll
Reply via Boardmail
Report problem with this ad
macdizzle
Previous username
mckaya
Bio page
macdizzle
Joined
Aug 31, 2010
Last login
Apr 18, 2024
Total posts
16,158 (117 FO)
Report problem with this ad
Messages
Author
Time
What would the order of subcontractors be to finish a basement?
macdizzle
2/17/20 5:40pm
I'd put plumbing before electrical.
Niiineteeen84
2/17/20 5:42pm
Good. Anything else?
macdizzle
2/17/20 5:44pm
I'd probably do framing before HVAC unless you're certain you won't need any air
Niiineteeen84
2/17/20 5:58pm
Framing, HVAC, Plumbing, Electrical, Drywall, Painting, Flooring (if tile/wood)
Fatalplacebo
2/17/20 6:00pm
Oh if a bathroom: Bathtub after framing, Toilet/sink after countertops
Fatalplacebo
2/17/20 6:05pm
Don't forget insulation.
Niiineteeen84
2/17/20 6:05pm
Dang it! Yes, put that in before drywall. It tends to be easier that way.
Fatalplacebo
2/17/20 6:07pm
Development office will give you guidance when you pull the permit.
WDaddy
2/17/20 6:05pm
*If you get a permit. County can't tax what county don't know