Put up the rails today. Went very quickly, about one hour working by myself with my wife handing them up to me.
Tomorrow the panels go up. Probably a 3 man job getting them up on the roof and placed.
Then drill the hole for attic access and start running conduit to the basement.
I still need to ask the building safety office if I can just wire into my basement panel instead of outside at the main service panel. Would save me a couple hundred in wiring and a couple hours of work. Rocky Mountain Power doesn't require an exterior disconnect on installs less that 10kW so I think I should be able to do it.
Hoping to have it all wired up by the end of next week.